Airlines impacted by new aircraft delays

By Vincent Valery

Introduction  

June 6, 2022, © Leeham News: LNA recently discussed the certification delays on all the current aircraft or variants under development: Airbus A321XLR, Boeing 737-7, 737-10, and 777X. Dreamliner deliveries have also been halted for 18 months now (except for a dozen last year).

Credit: Boeing

Airlines consequently face significant delivery delays on the aircraft they ordered. American Airlines publicly stated the Boeing 787 delivery delays have caused it to operate a smaller international network than envisioned. Air Lease Corp repeatedly noted that every airplane on order from Airbus and Boeing is delayed. It’s now been reported that CFM LEAP engines for the Airbus A320neo and Boeing 737 MAX families will be delayed for 4-6 weeks.

As passenger traffic recovers, the delivery delays will hamper airlines’ ability to capitalize on more robust demand. Higher fuel prices also mean that they cannot mitigate the impact by operating as many newer-generation aircraft as envisioned.

LNA analyzes the delivery schedule envisioned by Airbus and Boeing on the above programs that were in place before the delay announcements. The goal is to single out the most affected customers.

Summary
  • Deliveries concentrated with one customer on the 737-7 and 737-10;
  • A more diverse A321XLR and Dreamliner delivery base;
  • Renegotiating 777X delivery timelines.

Concentrated customer risks

Boeing 737-7 deliveries were supposed to start earlier this year with Southwest Airlines. In its 2022Q1 filing, the Dallas-based carrier disclosed that it would take 21 737-7s this year instead of the 72 envisioned at 2021 year-end. The adjustment suggests deliveries won’t start until well into the second half of 2022. Southwest swapped 40 MAX 7 orders for MAX 8s in response.

Boeing 737-10 deliveries are supposed to start next year. However, if Boeing does not receive certification for the variant by year-end and no regulatory relief is forthcoming, it would require a significant re-work that would materially delay certification.

It is reasonable to assume that the current certification delays on both variants will impact delivery schedules until at least 2024.

The below chart shows the breakdown of deliveries by the operator over the 2022-24 period for the 737-10 and 2023-24 for the 737-10:

Southwest is unsurprisingly the most exposed carrier to further 737-7 delays. Allegiant and WestJet are the only two other carriers that intend to take the variant over the period.

United Airlines is the most vulnerable carrier to a 737-10 certification delay. In 2023 only, United plans to take 109 737-10s, more than two-thirds of the variant’s scheduled deliveries for that year. The Chicago-based carrier plans to take delivery of 148 units over 2023-24 in total.

Exposure is more evenly spread among customers

Airbus announced an entry into service delay to 2024 for the A321XLR. The delay will at least impact deliveries scheduled in 2023 and 2024.

The ongoing production delays have led to more than 100 Dreamliners in inventory awaiting delivery. The production line is currently at a very low rate of 0.5 per month.

Once 787 deliveries resume, the FAA will have to sign them off like the 737 MAX. The requirement of FAA certification partially explains why Boeing has not been able to clear its 737 MAX inventory as quickly as envisioned. It also takes about two months per airplane to “wake up” and prepare a MAX for delivery from the legacy inventory, market intelligence reports.

It is reasonable to expect Dreamliner deliveries will be at a moderate pace for several months in light of the above and the need to clear a large inventory. Therefore, at least deliveries through 2023 will be affected.

The below chart shows the breakdown of scheduled deliveries for the A321XLR and 787 by the aircraft operator over 2023-24 and 2022-23, respectively:

North American carriers represent 62% of scheduled A321XLR deliveries over 2023-24. The most exposed carriers are American Airlines, United Airlines, and IAG (Aer Lingus and Iberia).

Boeing intends to build 77 Dreamliners in 2023, which implies a monthly production rate of 6.5. The delivery schedule looks ambitious in light of the 737 MAX precedent, and the line was at five per month before the drastic slowdown.

The most exposed carrier to the Dreamliner delivery delays is American Airlines, followed by Korean Air and Qatar Airways.

Another major round of 777X delivery rescheduling

After publishing its 2022Q1 earnings and announcing the 777X certification delay, Boeing removed 55 orders from its backlog as per ASC 606 rules.

Like in early 2021, when the first significant 777X delay was announced, Boeing is removing orders from the backlog where it knows it won’t be able to meet the contractual delivery date agreed with customers.

Until a few weeks ago, Boeing envisioned starting 777-9 deliveries in late 2023. Now, deliveries won’t begin until 2025. Therefore, deliveries scheduled over 2022-25 are impacted by the latest round of delays.

Below are the scheduled deliveries by the operator:

All identified 777X customers have deliveries scheduled by the end of 2025. Lufthansa’s 777-9 deliveries were all during this period. Half of British Airways’ deliveries are also over the period.

Combining 777X and Dreamliner compensation discussions

All the identified 777X customers except Cathay Pacific have Dreamliner deliveries scheduled by the end of 2023. Therefore, negotiations and compensation will likely involve rescheduling deliveries on both programs.

Lufthansa already negotiated with Boeing by ordering seven 777-8Fs and another seven 787-9s. The next monthly Boeing orders and deliveries update will indicate whether a portion of Lufthansa’s order was re-added to the backlog.

Emirates publicly discussed the possibility of canceling its Dreamliner order. After the latest delay, Etihad, which wishes to cancel its 777X order, might finally do so.

 

 

9 Comments on “Airlines impacted by new aircraft delays

  1. Leasing companies are not listed as they normally are found in order backlogs of popular models.

  2. Today I heard a rumor that a North American company (which is not Delta) will order an A330-900 this year. Does anyone know if this is true?

    • It would not be United or American since they have B787 in multiple lengths… I’d guess JetBlue.

        • I searched around a bit, and I did find a couple earlier references (3 years or so ago) to JetBlue being interested in that plane. It has also been reported that JetBlue is/was interested in Spirit so it would have access to more planes. Granted that would be narrow bodies, but in addition their A321LRXs are delayed. These were to be used to initiate Trans-Atlantic flights. So the case may be made that JetBlue is quite interested in expansion.

          I thought Hawaiian Airlines had committed to the B787. But they do fly the A330, and Boeing is having delivery issues, so it could easily be them. I would have no other guesses, unless it is a Canadien airline.

  3. Probably not Hawaiian, they were looking for the range of the A330-800. besides 10-20 aircraft is a large number for Hawaiian?

    To be frank, I’m surprised more airlines haven’t ordered the A330-900. Excellent, reliable aircraft and the only new widebody without major problems.

    As a passenger, i also much prefer the A330 over the 787.

  4. I went to check out the “rumor” and it seems that the interested North American company may not necessarily be from the USA. In this case, I thought of Air Transat.

Leave a Reply

Your email address will not be published. Required fields are marked *