The WAG estimate for lost revenue to Boeing for the delays of the 787 program is around $30 billion through 2013, based on some production estimates from a Goldman Sachs report issued this morning.
Goldman predicts $3 billion in penalty payments.
Goldman revised its delivery forecast, based on the Boeing program update conference call Wednesday, from 629 airplanes through 2013 to 407 airplanes. This forecast, by aerospace analyst Richard Safran, shapes up this way:
GS Current Assumption
2009: 25
2010: 60
2011: 85
2012: 120
2013: 120
Total: 407
January 2008 assumption
2009: 109
2010: 120
2011: 120
2012: 140
2013: 140
Total: 629
Difference: 222
We took these figures and applied it to Boeing’s list prices for the 787-8 and 787-9. Goldman’s data doesn’t break out how many of each type might be delivered during these years, so we calculated the average price of both models. At the low end based on all 787-8 deliveries, Boeing’s lost revenue during this period is $35.96 billion. Based on all 787-9 deliveries, the average lost revenue is $43.18 billion.
Applying an average 25% discount, which is not atypical in deals, the low end revenue loss is guesstimated to be $26.97 billion and the high end revenue loss is guesstimated to be $32.38 billion. Taking a somewhat middle-ground figure, we settled on $30 billion in lost revenue through 2013.