Boeing 737 MAX 2020-23 backlog will require to 2026 to deliver: analysis

Subscription Required

Introduction

By Scott Hamilton

Feb. 14, 2020, © Leeham News: It will take Boeing years to deliver new production airplanes scheduled for delivery in 2020-2023 because the restart of the 737 MAX production will fall far short of delivery commitments.

There are an estimated 2,682 deliveries scheduled in this timeframe. Boeing’s production restart and ramp up provides delivery positions for an estimated 1,827 aircraft. This leaves an estimated 855 aircraft that will have to be rescheduled into the future, from 2023.

These will compete with Boeing sales for new order delivery slots. For example, the MOU for 200 MAXes from IAG, the parent of British Airways and other carriers, has delivery slots in these periods.

An analysis by LNA indicates it will take at least until 2026 to deliver these 855 airplane if no other orders are slotted in through 2025.