January 39, 2026, ©. Leeham News: We have done a series about ideas on how the long development times for large airliners can be shortened, while at the same time describing all the regulatory work that must be done, regardless of work practices.
It’s now time to sum up what we have looked at in terms of speeding up the development of a Part 25 Air Transport airliner in the 200-seat segment. But before we do that, we will look at what an operator of the aircraft we have delivered will have to do to qualify it for operation with its local regulator.
For an operator to operate our aircraft, Continued Airworthiness, as described in last week’s article, is not enough; the Operator must add what can be called Continuing Airworthiness. These words are close but not the same, and there is a substantial difference in what’s behind them.
January 23, 2026, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have looked at the preparation work around entry into service; now we talk about post-certification work and the support of the new airliner generating revenue flights for the airline customer.
** Special thanks to Andrew Telesca for helping with this article **
January 16, 2026, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have looked at the production preparations and the challenges of the serial production phase. Now we look a the preparation work around entry into service for our new airliner.
January 9, 2026, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have completed flight testing of the flight test aircraft and obtained a design Type Certificate (TC). We now examine the production preparations and the serial production phase.
December 19, 2025, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have concluded the articles about flight tests with the aircraft. Now we revisit the Certification subject and look at how we can show compliance with requirements and work our way to a Type Certificate. We are at the end part of the Testing and Certification phase in our Program Plan in Figure 1.
** Special thanks to Andrew Telesca for helping with this article **
December 5, 2025, ©. Leeham News: We do a series on ways to shorten the long development times for large airliners. New projects aim to cut development time and achieve certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and the different approaches to reducing development time.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have exited the Detailed Design phase after conducting Critical Design Reviews, CDRs, and now enter into Prototype Manufacturing. After reviewing the acceptance and testing of the first parts and systems from suppliers, we now discuss putting together the first flight-test aircraft.
** Special thanks to Ron Everlove for helping with this article **
November 28, 2025, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We have exited the Detailed Design phase after conducting Critical Design Reviews, CDRs, and now enter into Prototype Manufacturing.
** Special thanks to Ron Everlove for helping with this article **
November 21, 2025, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We are in the Detailed Design phase, and it’s time to conduct the Critical Design Reviews, CDRs.
November 14, 2025, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times.
We will use the Gantt plan in Figure 1 as a base for our discussions. We are in the Detailed Design phase and working with the Certification Compliance plan.
*** Special thanks to Andrew Telesca for helping with this article ***
October 31, 2025, ©. Leeham News: We do a series about ideas on how the long development times for large airliners can be shortened. New projects talk about cutting development time and reaching certification and production faster than previous projects.
The series will discuss the typical development cycles for an FAA Part 25 aircraft, called a transport category aircraft, and what different ideas there are to reduce the development times. We will use the Gantt plan in Figure 1 as a base for our discussions.
We have exited the Preliminary Design phase through the Preliminary Design Reviews, PDRs, and now enter the Detailed Design phase.