August 6, 2021, ©. Leeham News: Last week, we went through the OTA, Authorization To Offer milestone.
Now we look at another important milestone in the Pre-Launch phase, the design Certification application. It involves some tricky differences in rules and procedures between the primary Certification authorities.
July 30, 2021, ©. Leeham News: Last week, we went through the later tasks in the Prelaunch Phase. We talked about Concept refinement, Supplier selection, and Certification work.
Now we dig deeper into the important Authorization To Offer (ATO) milestone. This is where the project starts to promise stuff to customers and others, and it can be both good and bad.
July 23, 2021, ©. Leeham News: Last week, we went through the initial tasks in the Prelaunch Phase. We talked about Sales and Marketing activities, initial Concept development, and first Supplier contacts.
Now that time has passed, we are three quarters into our Program Plan (Figure 2), and we have to refine our Concept, select Suppliers, and dig deep into how to get Certification.
July 16, 2021, ©. Leeham News: Last week, we showed the first cut of an overall Program Plan for our 19 seat airliner project.
Now we discuss the Prelaunch Phase activities in more detail, including what type of knowledge, tools and resources we need to get on board for the project.
July 9, 2021, ©. Leeham News: Now that we have done the basic market research we should scope the program. To do this we need to understand what aircraft we will develop and to what certification rules.
Our market research tells us to develop a 19 seat aircraft that can operate as a passenger and/or cargo aircraft outside the US and as cargo aircraft in the US. This enables us to certify it to FAA Part 23 and the equivalent rules of other National Aviation Authorities where we want to sell the aircraft.
July 2, 2021, ©. Leeham News: It’s time to start our aircraft project, where we discuss aircraft development from preliminary planning to fleet support and look at how the certification rules influence our work.
The first part of any aircraft project should focus on understanding the market your project will enter. Our project idea is to develop a Green aircraft for the 19 seat passenger market.
Subscription Required
By Bjorn Fehrm
July 1, 2021, © Leeham News: In our Friday Corners, we analyze the development challenges of aircraft. We will launch a concrete project Friday where we intend to develop a 19 seat airliner. To make it interesting, it will be a Green aircraft. We focus on the Certification issues in the Corner series.
To complement it, we here look at the operating cost of a battery-based electric airliner, as there are costs that are often not presented to the public in the marketing of these alternatives. The operational costs for the huge batteries are too often forgotten.
Figure 1. Heart Aerospace ES-19 battery based airliner. Source: Heart Aerospace.
June 25, 2021, ©. Leeham News: We are closing in on our aircraft project, where we will go through an aircraft development from A to Z and look at how certification rules govern our work.
Before we decide what aircraft to develop, let’s look at how the certification rules break the market into segments based on cabin seating.
June 18, 2021, ©. Leeham News: We continue our discussion about the Transport Category (FAA Part 25) certification rules.
Last week we talked about how much tougher the birdstrike protection is for Part 25. Now we look at the fuel tanks and the inherent explosion risk in these.