Irkut MC-21 rolls out

June 9, 2016: Irkut rolled out its challenger to the Airbus A320 and Boeing 737-800/8

MC -21 rollout. Photo: AIN Online via Google images.

yesterday the MC-21-300.

The new airplane is powered by either the Pratt & Whitney GTF or a Russian engine. A report from a Russian-sponsored media site is here.

LNC previously published an analysis of the economics of the MC-21 behind our paywall. We’ve opened up the first of four parts to all readers here.

UTC media day 2: GTF hits 99.5% dispatch reliability rates

June 7, 2016: The new Pratt & Whitney Geared Turbo Fan, on seven Airbus A320neos,

Bob Leduc, president of Pratt & Whitney.

have achieved more than 2,000 revenue cycles with no returns or rejected take-offs, says Bob Leduc, president of Pratt & Whitney. The engines have a 99.5% dispatch reliability. The last time this level was achieved was with the introduction of the Boeing 777, which at the same point had a 100% dispatch reliability rate.

Read more

UTC media day 2: PW addresses Under-Performing supply chain

Day 2 of the United Technologies Corp (UTC) Media Days is focused on Pratt & Whitney.

June 7, 2016: Pratt & Whitney officials today clarified an eye-popping statement yesterday by Greg Hayes, CEO of parent United Technologies, that 44% of the suppliers on the new Geared Turbo Fan engine were performing to goals.

Read more

UTC media day 1: Intelligent aircraft, aftermarket support

June 6, 2016: Intelligent aircraft–systems that communicate more fully within the aircraft

Mauro Atalla, UTC Aerospace Systems

and between the aircraft and the ground–is increasing and it requires more and more power to achieve, says Mauro Atalla, vice president, engineering and technology-sensors and integrated systems of UTC Aerospace Systems.

Intelligent sensors on an aircraft have been reduced in the number on board an aircraft even as the needs greatly increase, he said. There has been a reduction of more than 50%, providing a 50% weight reduction.

Read more

UTC media day 1: UTAS, twice the size of any other aerospace systems company

Note: United Technologies Corp (UTC) is holding its annual Media Days today and tomorrow. We’re providing reporting from the event. This is the first time in our long participation that UTC Aerospace Systems is presenting. UTAS is a major supplier and service provider to all the airframe OEMs.

June 6, 2016: UTC Aerospace Systems is just four years old, following mergers with

Dave Gitlin, CEO of UTC Aerospace Systems (UTAS).

Hamilton Sundstrand and Goodrich–the largest in aerospace history, says Dave Gitlin, president of UTC Aerospace Systems.

UTAS provides electrical power and bleed air systems, engine, starters, power systems, all the circulating fans on the Boeing 787, monitoring systems and much more. Evacuation slides, the Ram Air Turbines, landing gear, flaps and slat control systems, brakes and thrust reversers.

Read more

Airbus aircraft programs in review

By Bjorn Fehrm in Hamburg

Introduction
May 31, 2016, ©. Leeham Co: Airbus went through a complete review of all their aircraft programs as part of their yearly briefing for media in Hamburg today. A lot was said regarding the status for the different programs by Airbus CEO Farbice Bregier, its COO customers John Leahy and Executive VP Strategy and Marketing Kiran Rao.

csm_A350_XWB_Cathay_Pacific_TAKE_OFF_c87819faa2

Figure 1. Most recent A350 delivery was to Cathay Pacific. source: Airbus.

The briefing was given against a backdrop of weak orders and deliveries for the first five months of the year. Both Bregier and Leahy said, “This is to be expected, it’s not sustainable that we have Book-to-Bill ratios (orders vs. deliveries) of over 1.5 or even close to two for many consecutive years. We have a backlog of 6,700 aircraft that customers expect us to deliver and they have little appetite to order new aircraft when they can earliest get them by 2021 at the earliest.

“We are now in a period of focus on deliveries and we can expect and be happy with a book to bill ratio of around one for the coming years. The extraordinary backlog also justifies our decision to increase production to 60 units per month for our A320 single aisle program.”

Here follows what was said for each of the programs.

Read more

Airbus will recover 2016 production

By Bjorn Fehrm in Hamburg

Introduction
May 30, 2016, ©. Leeham Co:

Airbus has got off to a slow start for A320neo and A350 production this year. The Airbus Hamburg and Toulouse airfields are filled with A320neo aircraft waiting for engines and the A350 Final Assembly Line (FAL) in Toulouse has 40 aircraft in different states of readiness but very few are being delivered. Out of target of 50 A350 delivered in 2016, a total of nine have been delivered to customers so far.

Tom Williams

Airbus COO Tom Williams. Source: Airbus

“We have been making gliders for some time now,” said Airbus COO Tom Williams in an Airbus briefing in Hamburg,”but that is about to finish. We are getting delivery of engines from our partner Pratt & Whitney, which has a fix for a prolonged starting time and we have fixed other issues for the A320neo with software updates and changed procedures”.

“When it comes to A350 we have enough aircraft in final production ready for customer delivery after cabin installations,” Williams said. “Now we just got to work through some persistent supplier problems for the cabin side.”  Read more

E190-E2’s first flight

May 24, 2016: Embraer’s E190-E2 had its first flight yesterday, several months ahead of the internal schedule (original plan was September) making it the only new airplane program in recent history to be significantly ahead. Boeing’s 737 MAX was on time or a day or two early for its first flight.

The E2 is Embraer’s entry into the next phase of the E-Jet development, It’s powered by the Pratt & Whitney GTF engine. The airplane has new wings, new empennage, enclosed main gear, a digital Fly-By-Wire (FBW) and other improvement over what is now called the E1.

The flight was remarkably productive as the crew could fly the test aircraft’s envelope to M 0.82 and 41,000 ft, which is the aircraft’s max speed/altitude. The crew also flew the FBW in Normal mode (includes augmentations and protections) after having started in Direct mode, a more normal mode for a first flight.

What was achieved was far more than what is usual in a first flight. It shows a high confidence in the aerodynamic and structural design of the aircraft and the maturity of the FBW. The concern when testing higher speeds/altitudes is the flutter risk for the new wing and empennage, a very dangerous aerodynamic/structural oscillation that can destroy the parts. Embraer must have advanced its flight test technology as well to clear the flutter envelope in real time during the flight.

Paulo Cesar Silva, the CEO of Embraer Commercial, told us that the E2 is “100% on time and 100% on budget” during our interview for our column at Forbes on-line in which he characterized Bombardier as a “government-owned” company.

The E190-E2 is scheduled to enter service in the first half of 2018. The larger E195-E2 follows by a year and the smaller E175-E2 a year after that.

Egyptair 804

Read more

Mitsubishi’s MRJ test flying making good progress

By Bjorn Fehrm in Tokyo

May 18, 2016, ©. Leeham Co: Mitsubishi Aircraft Corporation (MAC) announced that their MRJ flight test program is now going well. Mitsubishi presented the status update at the International Society of Transport Aircraft Traders conference (ISTAT 2016 Asia) in Tokyo.

Mitsubishi RJ

Figure 1. Mitsubishi Regional Jet (MRJ) during flight testing. Source: Mitsubishi.

Mitsubishi Aircraft rocked the confidence of the market with announcing a delay in their program of over a year before Christmas. At the same time, MAC also announced that they will rebuild their test aircraft as they had seen that the original design did not meet ultimate load criteria.

As presented in one of my Friday Corners, that announcement was being too forthcoming. Other OEMs would not have informed the market of the minor modifications needed to make the aircraft able to withstand ultimate load (150% of the highest load the aircraft should ever see in service).

MAC’s Director of Strategic Marketing, Hideyuki Kamiya, gave an update of the flight test program at the conference and later answered some specific questions from LNC on the sidelines of the conference. Read more

Pontifications: Derivatives at Boeing

Hamilton KING5_2

By Scott Hamilton

May 9, 2016, © Leeham Co.: Last week proved to be significant when the CEO of The Boeing Co. and the head of the 737 MAX program each said the company is looking at revising its smallest member of the family, the MAX 7, and potentially enlarging the biggest member, the MAX 9.

Neither prospect was news. Jon Ostrower of The Wall Street Journal revealed the prospect of what he called the MAX 7.5, a slightly larger airplane than the current MAX 7. The idea of an airplane larger than the MAX 9, based on the MAX 9, was floated when Jim McNerney was still CEO.

What was news is that for the first time, the Boeing CEO and the head of the MAX program went on record essentially admitting the MAX line isn’t well positioned against Airbus after all. Or, on the lower end, to Bombardier.